If a project task must be completed on time in order for the entire project to be completed on time, the task is ____.

Respuesta :

metchelle
metchelle metchelle
  • 05-04-2017
The answer that fits the given blank above is LATEST FINISH TIME or LFT. This is the term that refers to the time when a project task should be completed in order for the whole project to be finished on time. Therefore, the task is now in its latest finish time. 
Answer Link

Otras preguntas

Conduct online research and locate your state’s preschool licensing authority website. Search for three licensed programs within your area and provide a short d
The half-life period for a first order reaction is independent of1) rate constant2) Concentration​
Consider points a, b, and c in the graph. Determine which of these points is relative maxima on the interval x = –1 and x = 2 in the graph.
Jim, Katrina, Larry, and Jim have all been invited to a dinner party. They arrive randomly and each person arrives at a different time. a. In how many ways can
Choose two values or traditions of the Village of Umuofia. Describe why this value/tradition is important and what it teaches you about the community. I Need h
find the nth term 16,25,36,49
tan(3x/7 - π/5)= -√3/3
How to treat coronavirus without medical treatment?
muslims???help plzz z z z
1. Lan is tall. (Mai) => ................... 2. I am tired. (I) => ................... 3. He is a teacher. (I) => ................... 4. She is a stude