sue, an experienced shipping clerk, can fill a ertain order 9 hours. Jim, a new clerk, needs 10 hours to do the same job. working together how long will it take them to fill the order?

Respuesta :

nobillionaireNobley
nobillionaireNobley nobillionaireNobley
  • 27-11-2016
Let x be the time required to do the job when they work together.
1/x = 1/9 + 1/10 = 19/90
x = 90/19 = 4.7 hours
Answer Link

Otras preguntas

What are disks in math? The question says use disks or disks on a place value chart to compare the numbers
What is a terminating decimal
what is the average of 23,33,17,28,34,27
What is one reason that Roger Williams wrote A Key into the American Language?
447,077 is_______ than 347,077
To raise money for new uniforms, the band boosters sell t-shirts and hats. The cost and sale price of each item is shown. The boosters spend a total of $2,000 o
what crisis nearly caused economic collapse in the empire
How did African Americans help strengthen the republican party in the south?
If tommy has two polo shirts and one gets stained and he throws it away how much polo shirts is he left with ?
mark tossed six ball while playing a number game. Three ball in landed in one section and three ball land in another section his score is greater than one hundr