A system has three components in parallel with reliabilities 0.9, 0.7, and 0.5. System reliability is:______

a. 0.315
b. 0.700
c. 0.900
d. 0.985
e. 2.100

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 23-12-2020

Answer:

0.985

Explanation:

A system contains three components that are arranged in parallel, they include 0.9, 0.7 and 0.5

Therefore the system reliability can be calculated as follows

= 1 - (1 -0.9)×(1-0.7)×(1-0.5)

= 1 - 0.1×0.3×0.5

= 1 - 0.1×0.15

= 1 -0.015

= 0.985

Hencd the system reliability is 0.985

Answer Link

Otras preguntas

Is 48 a perfect cube? Explain your reasoning.
Question 9 of 10 2 Points Which of these currencies is used in Switzerland? O A. The yen O B. The pound sterling O c. The franc O D. The yuan SUBMIT
A client who is diagnosed with seizures describes feeling a strange sensation before losing consciousness. The family members report that the client has been sm
2(1 – 8x) = 1/2 (8 - 64x)​
Why is project scope management so challenging in IT projects?
If policymakers are concerned that the economy is in danger of rising inflation because aggregate demand is increasing faster than aggregate​ supply, the approp
how do aerobic exercise help prevent
What does the government do for its citizens
prove that this question:.​
Show how the importation of opium from Vietnam is linked to the rise of drug use in the inner cities in the 1970s.