30 workers can complete a work in 40 days in how many days would 20 men complete the construction​

Respuesta :

s1m1
s1m1 s1m1
  • 25-11-2020

Answer:

27

Step-by-step explanation:

(30 workers/40 days) = (20 workers/x days) cross multiply

30*x=40*20 divide by 30 both sides

x= 800/30

x≈26.67

So they will need 27 days

Answer Link

Otras preguntas

Women who become pregnant during __________ are more likely to have premature deliveries. menopause midlife adolescence illness
Which is the correctly punctuated sentence? If you must bring a folder at least bring the smaller one. If you must bring a folder, at least bring the smaller
Explain how goal setting affects a person's motivation...
Write these numbers in order from least to greatest. ( 3-3/10), (3.1) , (3-1/4)
A closed economy has income of $1,000, government spending of $200, taxes of $150, and investment of $250. what is private saving?$100
a group of employees wishes to start a union is that lawful or unlawful explain
whats the surface area of the cube ​
What are some examples of uses of minerals? (Select 3 choices ) 1. SALT 2. Soda can 3. Toothpaste 4. Applesauce 5. Wooden craft stick
find the area of the shaded circle.give your answer in 3 significant numbers​
A factory worker earns $150 each day plus $5.25 for each widget that he makes. If he earned $370.50 for one day of work, how many widgets did he make? 3 42 64 7