Planned value:

How is it calculated?

Respuesta :

ZaWarud0
ZaWarud0 ZaWarud0
  • 21-10-2020
Take the planned percentage of the completed work and multiply it by the project budget and you will get Planned Value.
Answer Link

Otras preguntas

Is an extended school day the right choice for middle school students?
In which type of environment are plants most likely to use a C4 pathway of carbon fixation A) cold and wet B) cold and dry C) hot and wet D) hot and dry
When people are placed into groups based on physical or biological traits that they have inherited, they are being classified by __________. a. ethnicity b. g
what letter grade would 56% be
Our verbal and nonverbal blank provides clues to our attitude on a given topic
Three of these methods gives the correct area of the figure. Which method does NOT? A. add the areas of two half circles and a trapezoid B. add the ar
Anastasia is grocery shopping with her father and wonders how much shopping is left to do. "We already have 60%, percent of the items on our list," her father s
what's the final volume of a gas with an initial volume of 75ml if the pressure decreases from 300ml to 200ml? A. 50.0ml B.112.5ml C.100.0ml D. 75.5ml
in what way was the first crusade, launched in 1095CE , similar to the third crusade, launched nearly a century latera. Both expanded the territory of christian
In the sentence "Mary caught a frog," the common noun serves as a. the subject of the sentence. b. both subject and object. c. the verb of the sentence. d.