if 8 people can pick the apples from the trees in 6 days, how long will it take 12 people

Respuesta :

mhanifa
mhanifa mhanifa
  • 24-06-2020

Answer:

4 days

Step-by-step explanation:

8 people can do the job in 6 days, job is this case is picking apples.

  • The amount of the job (apples) is same and the only variable is number of people which changes the time accordingly.  

1 person can do same job for 6*8= 48 days

12 people can do same for 48/12= 4 days

Answer Link

Otras preguntas

You heat a piece of iron from 200 to 400 K What happens to the atom's energy of random motion
a dog groomer could clean five dogs in an hour. how many could they clean in two sixths of an hour?
why were roads significant to the roman republic and ancient cultures and religions of the same time period
Where does cellular waste get removed?
What is the highest mountain in the United States and where is it located in the West region?
how to factor 16x²-72xy+81y²
Is the group of words a simple sentence, a compound sentence, or a run-on sentence? The forests were cleared, soil is eroding there.  A.run-on sentence  B.simpl
your body makes more carbon dioxide when you run than when you sit still why
Suzanne needs material for her school project she buys 4.75 yards of material at $5.37 a yard what is the total cost of material round to the nearest cent a.$25
when naoh(aq) reacts completely with hcl(aq) and resulting solution is evaporated to dryness the solid remaining is?