Qn.11 plz help this with step ​

Qn11 plz help this with step class=

Respuesta :

salatulmaghrib
salatulmaghrib salatulmaghrib
  • 25-07-2019
The answer is 7.5 days
explanation:
80 is four times 20.
80 people should be able to do the job four times faster than 20 people.
So, they should take 1/4 the time.
If 20 people take 30 days, 80 people should take 30/4=7.5 days.
**
simpler explanation:
30*20/80=7.5
Answer Link

Otras preguntas

PLEASE HELP ASAP! 10 PTS.!!WILL MARK BRAINLIEST!PLEASEEE HURRY DUE IN 2 MIN!You are delivering a speech to your classmates urging them to donate blood. As you
How did the role of slavery change in missouri from the 1840s to the 1870s?
Based on the name of the muscle pronator teres, what can you tell about it? check all that apply. its shape its action its number of muscle heads its body regio
how does the dark bring harm to people?
The rectangle to the left is divided into 12 shapes. One of them is a rectangle labeled with #1 and the remaining 11 shapes are squares. The length of the side
what tried to resolve issues reguarding the united states and indians
Can any one help me with 45 and 46 please
High doses of stimulants can influence driving capabilities by
The transmission coefficient of the hypothetical disease dumas fever is 0.2. if the combined death and recovery rate is 0.4, what is the threshold density for d
Two chlorides on the carbon of a methane unit are called: (choose one) -methyl chloride -dichloromethane -chloroform -carbon tetrachloride