is the difference between the finish date of the last activity on the critical path and the project completion date.
a. Lag time
b.Control limit
c. Total float
d.Contingency time
e.Forward pass

Respuesta :

Otras preguntas

On Monday, it took Helen 3 hours to do a page of science homework exercises. The next day she did the same number of exercises in 2 hours. If her average rate o
List all the Commonwealth Games mascots.
I'm having a hard time with this one solve for y 3y+7=28?
what are the worlds biggest countries?
X+2y+6=0Solve for the value of "y"And explain how to graph the result.
Solve by completing the square x^2-2x-5=0
To subtract two rational expressions that have a common denominator, you simply _____ the numerators.
The width of a rectangle is 5 feet, and the diagonal is 8 feet. Which is the area of the rectangle? (Round to nearest hundredth.)
Help me please, clandestine means.. 1. a sudden attack 2. one who bothers; to bother 3. take in as one s own 4. marked by or done in secret; stealthy
If trypsin and chymotrypsin become activated within the pancreas and then are released in their active forms into the bloodstream, why would this represent a po